Skykomish Cleanup  Home  |  Cleanup Activities  |  Background  |  Documents  |  Photos  |  Contact Us    
 
 
 
Upcoming Events
  July 3-5 No work (Independence Day weekend)
  July 7 Move Maloney's General Store; temporary 5th Street closure (1 day)
  Week of July 6 Overburden soil sampling & excavation
  Week of July 6 Start deep excavation
  Week of July 6 Site preparation for Skykomish Hotel

Skykomish cleanup schedule

SkyRiver Inn demolition [6/18/09]

BNSF Railway and the Department of Ecology completed the first phase of a significant environmental cleanup in 2007 in Skykomish, Washington. Beginning in June 2006, the Interim Action involved excavation and restoration of the Town’s flood control levee and nearby upland areas, and the removal of contaminated Skykomish River sediments.

In 2007, BNSF and Ecology finalized plans for the remainder of cleanup in Skykomish. The Cleanup Action Plan, part of a consent decree, guides the entire cleanup in Skykomish. This multi-year cleanup is conducted in phases concentrated in different parts of town. The majority of work in 2007 and early 2008 consisted of investigational activities such as sampling and surveying. Cleanup activities in 2008 included excavation as well as installing an underground barrier at the railyard to capture and treat contaminated groundwater.

Similar to 2008, cleanup activities in 2009 will include temporarily relocating houses and buildings to allow excavation of contaminated soils. BNSF and Ecology will continue to work closely with the Town of Skykomish to address impacts, obtain input, and keep people informed during the implementation of cleanup plans.

This website provides information and updates during cleanup activities. Check back often for updates and new information. Additional information on the overall cleanup project can be found in the background and documents sections of the website.

To stay informed about the cleanup project and work activities,
sign up for email alerts at info@skykomishcleanup.com, and visit the Department of Ecology website.

Recent Updates

Privy discovery and historic documentation
Crews discovered remnants of old privies in the excavation area. These sites will be roped off until archaeologists document and remove the contents (e.g. old bottles). Excavation of these areas will continue after historic contents are removed. The property owner will later be able to claim the contents.
Posted on 07/02/2009
Move Maloney's General Store; temporary 5th Street closure
Crews will move Maloney's General Store on Tuesday, July 7, to the former location of the SkyRiver Inn. Fifth Street will be closed to traffic and pedestrians while the building is moved. Crews will establish detours around West River Road. This work should take about a day.
Posted on 07/02/2009
Moved Bishop house
The new owner of the Bishop house moved the house to its permanent location on June 29.
Posted on 07/01/2009
Temporary closure/detour at 5th Street (1 day)
On Thursday, July 2, crews will set steel beams under Maloney's General Store in preparation for temporarily relocating the building. This work requires additional space to maneuver the beams, so crews will temporarily close 5th Street for one day. Traffic will be rerouted onto West River Road. The railroad crossing and the intersection of 5th Street and Railroad Avenue will remain open.
Posted on 06/30/2009
Site preparation for Maloney's General Store
Crews continue to prepare Maloney’s General Store for temporary relocation on July 9. Crews will move the Store to the former location of the SkyRiver Inn.
Posted on 06/25/2009
Community wastewater system
The Town of Skykomish will start construction on the community wastewater system in mid-July. Trenching will occur in one lane of Old Cascade Highway and at the intersection of 5th Street and Old Cascade Highway.
Posted on 06/25/2009
Site preparation for the Skykomish Hotel
Preparation continues for the relocation of the Skykomish Hotel on July 20. Crews will move the Hotel to the former location of the SkyRiver Inn office. This will provide enough room for the temporary bridge ramp that will be constructed when 5th Street is closed for excavation.
Posted on 06/25/2009
4th Street closure and excavation
Phase 1 excavation begins this week. This means a portion of 4th Street in front of the Skykomish Community Church will close on Monday, June 29. Residents will access their homes on 4th Street using East River Road or Railroad Avenue.

Excavation of overburden soils starts on Monday, June 29. Deep excavation (20 to 26 feet) is scheduled to begin the week of July 6. Oil recovery mobilization will begin the week of June 29.
Posted on 06/25/2009
Utility boring under railroad tracks
Crews are continuing utility boring under the railroad tracks. Power interruptions are not expected. This work may affect traffic at the 5th Street and Railroad Avenue intersection and flaggers will assist with traffic control as needed.
Posted on 06/25/2009
Relocate the Bishop house
The Bishop house will be relocated to its new permanent location on Old Cascade Highway. The new owner is expected to move the house on June 29. Traffic will be temporarily interrupted when the house moves across the railroad tracks; flaggers will assist with traffic control.
Posted on 06/25/2009
Move houses from 4th St to temporary location
The Martin house was moved to its temporary storage location at the east end of Railroad Avenue, just west of the Depot. The Sarno house will move to the same temporary location the week of June 22. Flaggers will be available to direct traffic if needed. These houses will be returned to their original locations this fall.
Posted on 06/19/2009
Demolish SkyRiver Inn and old post office
Demolition of the SkyRiver Inn will be completed this week and demolition of the old post office building will occur the week of June 22.
Posted on 06/19/2009
Sky River Inn
Site preparation continues at the Sky River Inn. Utilities will be disconnected the week of June 15 and demolition may happen as early as the end of the week.
Posted on 06/12/2009
Relocation of residents on 4th Street
Several residents were relocated from their homes on 4th Street this week. Utilities will be disconnected the week of June 15 and crews will prepare the structures for moving.
Posted on 06/12/2009
The post office is moving
Over the weekend of June 13, the post office will move to its new location on Thelma Street, near the corner of Old Cascade Highway at the former U.S. Forest Service compound. The post office will be closed on June 13 and 14, and will reopen in its new location on Monday, June 15. The post office will be at this location for at least two years.
Posted on 06/09/2009
Water bypass work
Crews will install a water bypass line under 4th Street starting on June 10. The line will be installed underground and primarily in Town right-of-way. Residents will be notified if they are expected to experience a brief interruption in water service.
Posted on 06/09/2009
Cleanup and Town prepare for Centennial celebration June 5-7
The Town of Skyokomish Centennial celebration will be held on June 5-7. Cleanup crews have been working with the Town to prepare for this major event. New temporary sidewalks, striping, and parking spaces have been installed along Railroad Avenue. Crushed rock has been used to create flat areas for booths on both the north and south sides of Railroad Avenue. The Town kiosk has also been temporarily reinstalled for the Centennial.
Posted on 05/29/2009
Community construction meeting: Thursday, May 28
Come learn about detailed construction plans for 2009. The project team will review construction phasing, potential impacts to traffic and how to stay informed about construction.
Thursday, May 28
6:00 to 8:00 p.m.
Maloney's General Store (104 Railroad Avenue, Skykomish)
Posted on 05/14/2009
Preparations for construction
Mobilization and construction activities will begin in May. Residents should expect increased truck traffic, construction fencing installation, and preparations for demolishing the SkyRiver Inn buildings. This week, HAZMAT surveys will be conducted on buildings that will be relocated or demolished. Crews will also apply Soil-Cement to unpaved areas of the rail yard for dust control.
Posted on 05/13/2009
Restoration updates, ATB paving
BNSF and its contractors continue to restore Town and private properties, and have been working with the Town of Skykomish and the Skykomish Historic Society to plan for the Centennial celebration. Permanent streets lights are now operational along Railroad Avenue. Crews will re-pave Railroad Avenue using asphalt treated base (ATB) beginning this week or the week of May 18. Some sidewalks will also be temporarily restored using ATB. This will improve roads for general use and for the Centennial celebration. Final street paving will occur after construction activities are complete.
Posted on 05/13/2009
BNSF selects Strider Construction to complete cleanup activities in Skykomish
In May, BNSF provided notice to award the general construction contract to Strider Construction. Contracting efforts are now underway. Strider was the prime contractor in 2008 and will be contracted through 2011 to complete cleanup and restoration work in Skykomish.
Posted on 05/13/2009
Public comment period ends (April 21)
Ecology is reviewing comments on the proposed amendment to the Cleanup Action Plan.
Posted on 04/24/2009
Wetland cleanup planning
Crews completed surveying work to help identify potential sampling locations in the Former Maloney Creek area.
Posted on 04/24/2009
Utility work continues
Verizon continues pulling lines through the joint utility trench.
Posted on 04/24/2009
Street lights installed
Potelco installed historic-looking street lights along Railroad Avenue.
Posted on 04/24/2009
Surveying
During the week of April 27, crews will survey areas around the 5th Street Bridge, the levee and on some private properties.
Posted on 04/24/2009
Planning for construction
BNSF is in the process of evaluating and selecting a contractor for cleanup work in 2009-2011. A public meeting will be held before construction begins to review detailed construction plans (date to be determined). Project engineers are also preparing for construction by completing additional survey work and property restoration in town.
Posted on 04/16/2009
Air sparging
The air sparging system on the Joselyn property is now operational. Monitoring activities will continue.
Posted on 03/26/2009
Community Meeting: Wednesday, March 25
BNSF is proposing changes to the Skykomish cleanup schedule and cleanup at the Skykomish School. A public meeting will be held on Wednesday, March 25 from 6-8 pm at Maloney's General Store (104 Railroad Avenue, Skykomish).

Join us to learn about changes to 2009 construction, cleanup activities in 2010 and 2011 and proposed revisions to the Cleanup Action Plan (CAP). The project team will review:

- Proposed revisions to the Cleanup Action Plan (public comment period: March 23 – April 21, 2009)
- 2009 – 2011 cleanup schedule
- Excavation and restoration
- Building relocation
- Home and business access.

Staff from BNSF, the Washington State Department of Ecology and the Town of Skykomish will be available to answer questions and take comments.
Posted on 03/16/2009
Joint utility trench (JUT) work
Work on the JUT will continue this week after being stopped for several days last week due to freezing weather. Paving the JUT crossings will begin Monday, March 9.
Posted on 03/02/2009
Joint utility trench (JUT) work
Crews will continue work on the JUT for approximately 3 weeks. The JUT will cross Railroad Avenue in several places but crews will ensure access is maintained during trenching. Upon completion of trenching, crews will finish the trench using asphalt-treated base material. Crews will install Verizon and PSE pedestals, street lighting bases, and other above-ground and flush permanent features that allow residents to utilize an underground utility system instead of overhead lines. This equipment will be placed on Town right-of-way adjacent to personal property in many places along Railroad Avenue and 4th Street. Notification will be provided prior to work near personal property.
Posted on 02/13/2009
Work on the HCC system continues
Gravel will be delivered on Friday (2/13) to use in the HCC system vaults along Railroad Avenue, and granular activated carbon will be installed in the vaults the week of February 16. Residents should expect some truck traffic, but access to all roads and buildings will be maintained.
Posted on 02/12/2009

 

The SkykomishCleanup.com domain is owned by BNSF.