Skykomish Cleanup  Home  |  2008 Construction  |  Background  |  Documents  |  Photos  |  Contact Us    
 
 
 
Upcoming Events
  7/21 Sheet pile driving at west end of RR Ave
  7/24 Community Meeting at the General Store (6-8pm)
  Week of 7/21 Excavation along Railroad Avenue continues
  Week of 7/21 Pre-excavation near the sheet pile alignment

Cleanup schedule

Sheet pile work along Railroad Avenue - [7/3/08]

In 2007, BNSF Railway and the Department of Ecology completed the first phase of a significant environmental cleanup in Skykomish, Washington. Beginning in June 2006, the Interim Action involved excavation and restoration of the Town’s flood control levee and nearby upland areas, and the removal of contaminated Skykomish River sediments.

BNSF and Ecology have finalized plans for the remainder of cleanup in Skykomish. The Cleanup Action Plan, part of a consent decree, will guide the entire cleanup in Skykomish. This multi-year cleanup will be conducted in phases concentrated in different parts of Town. The majority of work in 2007 and early 2008 consisted of investigational activities such as sampling and surveying. Cleanup activities in 2008 will include excavation as well as installing an underground barrier at the railyard to capture and treat contaminated groundwater. Similar to the work near the levee in 2006, some houses and buildings will be temporarily relocated to allow cleanup work to proceed. BNSF and Ecology will continue to work closely with the Town of Skykomish to address impacts, obtain input, and stay informed during the implementation of cleanup plans.

This website provides information and updates during cleanup activities. Check back often for updates and new information. Additional information on the overall cleanup project can be found in the background and documents sections of the website.

To stay informed about the cleanup project and work activities,
sign up for email alerts at info@skykomishcleanup.com, and visit the Department of Ecology website.

Recent Updates

Community Meeting on July 24
You’re invited! A public meeting will be held on Thursday, July 24, from 6:00 - 8:00 p.m. at Maloney’s General Store. Cleanup staff will provide information on cleanup progress and be available to answer questions.
Posted on 07/18/2008
Oil recovery
The oil recovery contractor will mobilize the week of July 14 and crews should being removing oil the week of July 21.
Posted on 07/11/2008
Work happening in town this Saturday
ENSR and Strider are evaluating how to increase the pace of construction to ensure work is completed on schedule. To meet this need, crews will start working some Saturdays, starting on July 12.
Posted on 07/11/2008
Excavation along Railroad Avenue continues
Continue excavating Railroad Avenue and removing overburden material. Soon, crews will begin to dig much deeper into Railroad Avenue to remove contaminated groundwater. This work is estimated to begin the week of July 21.
Posted on 07/11/2008
Pre-excavation near the sheet pile alignment
Crews will continue excavating the sheet pile alignment to remove any large boulders. This pre-excavation will continue through the week of July 14.
Posted on 07/11/2008
Sheet pile update
Thirteen sheet piles were successfully vibrated into the ground at the west end of Railroad Avenue after crews excavated the alignment. Excavating the alignment allows crews to vibrate sheet piles more easily into the ground and helps avoid the use of an impact hammer.
Posted on 07/11/2008
Temporary railroad crossing
A crossing guard is now stationed at the temporary railroad crossing at the west end of Railroad Avenue. This guard is not a BNSF flagger and will not have radio contact with the trains, but will assist motorists and pedestrians as they cross the tracks. -- The 5th Street railroad crossing closed on Wednesday, June 25. Traffic is rerouted to the temporary west crossing near the Skykomish School. The temporary crossing is open from 7:00 am to 10:00 pm every day. Pedestrians and drivers should remember to pay attention, look both ways and proceed safely.
Posted on 07/11/2008
No work during 4th of July weekend
Construction work will not take place on Independence Day weekend (July 4 – 6). However, weekend work may become necessary as the cleanup proceeds.
Posted on 07/04/2008
Sheet pile installation
The sheet pile alignment at the west end of Railroad Avenue was not pre-excavated because of the close proximity of railroad tracks. The sheet piles hit large boulders and crews were unable to drive them any deeper. Crews will remove the sheet piles and locate the alignment slightly north to allow pre-excavation and the removal of large boulders. Sheet piles will be re-installed on Tuesday, July 8.
Posted on 07/03/2008
WSDOT temporarily closing Old Cascade Highway bridge
WSDOT is temporarily closing the bridge at the west end of Old Cascade Highway on Tuesday, July 8. WSDOT estimates this work will take one day.
Posted on 07/03/2008
More parking for the Cascadia Inn and church
New temporary parking spaces are now located next door to the Skykomish Community Church and the Cascadia Inn, Cafe and Lounge.
Posted on 07/03/2008
Building relocation
The Depot was moved on Saturday, June 21, and the McEvoy house was moved from on Tuesday, June 24. Crews should relocate the Whistling Post by Saturday, June 28.
Posted on 06/27/2008
Overburden sampling
Crews continued sampling overburden material (e.g. excavated soil).
Posted on 06/26/2008
Water treatment facility installation
The water treatment facility was set up on the railyard. It will be used during construction.
Posted on 06/26/2008
Excavate portions of Railroad Ave and PSE power line work
Portions of Railroad Avenue will be excavated the week of June 23. Also, PSE will be moving power lines the week of June 23. Residents and businesses will be notified about when to expect temporary power outages.
Posted on 06/20/2008
Sheet pile driving will begin near the end of June
Delivery of sheet pile has begun. Piles will continue to be delivered by trucks and rail, and will be stored on the railyard. Sheet pile driving will begin sometime in late June. This work will be noisy and will cause vibrations along Railroad Avenue. A notice will be posted when a start date is selected.
Posted on 06/19/2008
Temporary water service interruption on Tuesday, June 17
Crews are preparing a temporary water bypass line for use during the cleanup this summer. As a result, a temporary water service interruption is scheduled for Tuesday, June 17, between 8:00 a.m. and 12:00 p.m. It will affect residents and businesses north of the railroad tracks. For more information, call the Skykomish Call Line at 800-228-1849.
Posted on 06/13/2008
Water line bypass installation along Railroad Avenue
Crews will continue to install a water line bypass along Railroad Avenue east of 3rd Street this week. This work will occur under the existing sidewalk along Railroad Avenue. Please be aware of any "No Parking" signs along Railroad Avenue.
Posted on 06/04/2008
Building movers in town
Starting the week of June 9, the building movers will be onsite to begin preparation activities for the buildings that will be temporarily relocated during this seasons cleanup work.
Posted on 06/03/2008
Pavement grinding along Railroad Avenue
Starting June 4, crews will grind the road surface of Railroad Avenue between 4th and 6th Street. There will be periodic closures of the 5th Street crossing this week.
Posted on 06/03/2008
Trailer demolished
Crews demolished a trailer on BNSF property along Old Cascade Highway.
Posted on 05/21/2008
Landscape and structural surveys complete
Landscape and structural surveys were completed on buildings that will be temporarily relocated in 2008.
Posted on 05/21/2008
Railyard limited excavation complete
Green Earthworks completed excavation and backfilling on the railyard. Crews swept and washed the streets along 5th Avenue to remove tracked dirt.
Posted on 05/21/2008
BNSF rail work
BNSF crews are in Skykomish for rail maintenance activities. Work should be complete in June.
Posted on 05/20/2008
Levee railing installation
Crews continued to install the new railing on the levee; work should be complete this week or next week.
Posted on 05/07/2008
Well abandonment
Monitoring wells in the 2008 construction area were decommissioned, or "abandoned."
Posted on 05/07/2008
Building surveys
Buildings that will be temporarily relocated this year were surveyed for any hazardous materials, such as asbestos or lead paint.
Posted on 05/06/2008
Mobilizing for 2008 construction
In addition to excavating limited areas of the railyard, construction crews are beginning to mobilize for 2008 construction work. Activity in town will increase over the coming weeks.
Posted on 05/06/2008
Contractor Job Fair
Strider Construction will be holding a job fair at the General Store on Wednesday, May 7th from 4 - 6 pm.
Posted on 04/30/2008
Contractor selected
BNSF has selected a construction contractor for 2008. Please join us in congratulating and welcoming Strider Construction to Skykomish.
Posted on 04/18/2008
Limited railyard excavation
Limited railyard excavation is scheduled for the week of May 5. A trailer on BNSF property north of Old Cascade Highway is also scheduled for demolition.
Posted on 04/18/2008
Levee railing installation
The levee railing is scheduled to be delivered the week of April 21. Installation will take approximately one to two weeks.
Posted on 04/18/2008
Well sampling
Three groundwater wells will be sampled on April 23. The wells are located on 4th and 5th Streets and Railroad Avenue. Work should take about a day.
Posted on 04/17/2008
Public meeting on Tuesday, April 29
BNSF, Ecology and the Town will provide more information on the construction work that will take place this year in Skykomish. The meeting is Tuesday, April 29 from 5:30 to 7:30 pm at Maloney's General Store, located at the corner of 5th Street and Railroad Avenue.
Posted on 04/15/2008
Public meeting on Wednesday, March 19
BNSF and Ecology will provide an update on cleanup and construction work that will take place this year in Skykomish. The meeting is Wednesday, March 19 from 6:00 to 8:00 pm at Maloney's General Store, located at the corner of 5th Street and Railroad Avenue.
Posted on 03/10/2008

 

The SkykomishCleanup.com domain is owned by BNSF.